Phased ERP rollout for small business: a staged plan

A phased ERP rollout for small business spreads risk across two to four go-lives. Here is the stage plan, the gates, the timings and the costs.

Before you ask

Phased ERP rollout for small business: questions, answered.

Can I go live with an ERP gradually?

Yes. You can phase by module, site, business unit or process. For most small businesses, going module by module works best: finance and master data first, then purchasing, stock and sales, then payroll or production.

Is a phased ERP rollout better than big bang for a small business?

Usually, when stock, payroll, several sites or many departments are involved. Phasing spreads risk but adds length and temporary bridges. Big bang suits one site, fewer than about 10 users and simple processes.

Which ERP modules should I implement first?

Start with master data and finance, because every other module relies on your items, customers, suppliers and chart of accounts. Then add purchasing, inventory and sales. Payroll or production usually comes last.

How long does each phase of an ERP rollout take?

As a rule of thumb for 10 to 50 users: discovery 2 to 4 weeks, finance 4 to 8, purchasing, stock and sales 6 to 10, payroll or production 6 to 10, and reporting 3 to 4. Expect about five to nine months overall.

What if one phase fails? Can I roll back?

Yes, and a small phase is cheap to roll back. Keep the old system read-only for a set period, agree the rollback trigger in advance, take a backup on the freeze date and run two to four weeks of hypercare.

When is the best time of year to go live with an ERP?

Start finance at the beginning of a month or quarter. Avoid year-end, stocktake and peak trading, never cut over payroll in the same week as finance, and leave two to four weeks between phases.